We would like to express our sincere sympathies with all of you who were struck by the 2011 off the Pacific Coast of Tohoku Earthquake that occurred on March 11th, 2011. We are hoping for the early revival in the area that is suffering from the disaster.
We hereby inform you of the current situation of the Shin-Etsu Group’s production sites, which were impacted by the earthquake, as below.
Current situation of Shin-Etsu Group’s plants being out of operations
As of 1:00p.m., March 22 (Japan Time), there has been little change in our situation since our 4th report dated March 17th. All of operations at both Shin-Etsu Chemical Kashima Plant (Kamisu, Ibaraki Pref.) and Shin-Etsu Handotai Shirakawa Plant (Nishigo Village, Fukushima Pref.) are being wholly halted. Although the aftershocks have been frequently occurring, we are to carry out necessary inspections at our plants putting the utmost priority on safety.
Regarding the situation of Shin-Etsu Handotai Shirakawa Plant, although we have not yet fully undertaken inspection work of all facilities and equipments, damages of the production facilities and equipments has been partially observed until now. At present, it is still unclear how long it takes to restore such damages. Therefore, we will set up production systems at other plants of Shin-Etsu Handotai Group except for Shin-Etsu Handotai Shirakawa Plant, so that we may respond to the current situation.
As for Shin-Etsu Chemical Kashima Plant, some damages of the production facilities and equipments have been observed until now. In addition, the Kashima industrial complex where the Kashima Plant is located in, received wholly heavy damages in its infrastructure such as the utilities as electric power and water supply and it may take time to re-start the supply of the raw materials. Thus, at present, it is still unclear how long it takes to re-start the operations at the Kashima Plant.
Furthermore, the rolling blackouts implemented by TOKYO ELECTRIC POWER COMPANY and Tohoku-Electric Power Co.,Inc., are affecting the operations at Shin-Etsu Group’s production sites located in their respective electric power supply areas. We will cooperate for reduction and restriction of the usage of electric power with all the Company efforts. Meanwhile, we are requesting the electric power companies to provide a stable supply of electric power because we have facilities and equipments that need to be operated continuously due to the safety reasons.
We will continue to do our utmost for recovery. We will announce the updated information if any situation has changed.
For inquiries about this matter, please contact
- Shin-Etsu Chemical Co., Ltd.
- Public Relations Dept.
- Tetsuya Koishikawa
- Tel: 03-6812-2340, or from outside Japan: 81-3-6812-2340
- Fax: 03-6812-2341, or from outside Japan: 81-3-6812-2341
- Contact us